Testing of Control System for Zagorskaya PSHPP Hydroelectric Unit

Date news: 8 June 2011
To the list of news

“SPC “Rakurs” Ltd. has implemented pre-delivery testing of Control System for Hydroelectric Unit No.3 of Zagorskaya Pumped-Storage Hydro Power Plant. The testing has been carried out at the company’s testing floor with participation of customer representatives. Tests has showed that the equipment meet the requirements. Control System has been shipped to Zagorskaya PSHPP.

The delivery included several cabinets of control system software and hardware complexes (SHC) for hydroelectric unit No.3 of Zagorskaya PSHPP:

- SHC for hydroelectric unit automatic control,

- SHC for measuring, warning and alarm;

- SHC for electric part of frequency and active power regulating system,

- SHC for hydroelectric unit auxiliary equipment control,

- SHC for hydroelectric unit temperature control,

- SHC for emergency closing of water gates.